Q1 How long will it take
to install the insulation cladding?
It really depends on the tank volume. For
an example, use this as a rough guide: A 45KL (10KGallon)
tank - Up to 3 can be clad per day. For the larger 280KL tanks
(60KGallon), it usually takes one day to clad each tank.
Back to top
Q2 What maintenance is
required after installation?
The cladding is virtually maintenance free
once installed. We normally recommend washing the cladding
with soapy water every 6 months to prevent build up of weathering
effects such as mould or staining. Of course, running into
the tank with a forklift may require some further maintenance...
Back to top
Q3 What is the expected
life span of the insulation cladding?
With correct maintenance, indefinite. We
are convinced that the cladding will last as long as the tank
itself. Because this technology is relatively young, we don't
have too much data regarding longevity. We do, however, know
that the earliest installations from 1984 are still going
strong today.
Back to top
Q4
What countries or areas has Polarclad serviced?
To name a few, we have implemented our technology
in countries such as: Australia, United States, New Zealand,
China and Vietnam.
Back to top
Q5
Will the installations interfere with my current operations?
The installations will not interfere with
your current operations. In fact, we have often installed
cladding during wineries busiest times such as Vintage Season.
The installations are performed with no fuss and minimal disruption.
Back to top
Q6
What areas of Australia will Polarclad service?
We will service all areas of Australia, including
all states and territories. Basically, any place where wine
is being manufactured and stored.
Back to top
Q7 Is the insulation
cladding vapour-sealed?
Definitely. The end result aluminium
cladding forms a full vapour seal.
Back to top
|